Mcpherson Furniture Company Case Study

266 Words2 Pages
Name Section Date (Capitalization of Interest) 10/10/2012 Exercise 10-7 McPherson Furniture Company E10-7 (Capitalization of Interest) McPherson Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2012. McPherson expected to complete the building by December 31, 2012. McPherson has the following debt obligations outstanding during the construction period Weighted McPherson Furniture Company Avoidable interest computation: (a) Construction Loan $ Average Accumulated Expenditures 2,000,000.00 Interest Rate Avoidable Interest 12% $ 240,000.00 Shorterm loan ** $ $ 1,800,000.00 3,800,000.00 10.38% $ 186,840.00 $